1 |
SEWAGE LINE PROJECT IN KING FAHAD DISTRICT WEST ABOU HADRIA ROAD DAMMAM |
United Works General Cont. Est. |
30008/ 684 |
25-Dee-17 |
MINISTRY OF ENVIRONMENT, WATER |
92,589,109.25 |
0.45% |
2 |
BAHR AL AHMAR BOULEVARD WORKS |
United Works General Cont. Est. |
104352 |
26-Jul |
EMAAR |
12,303,904.80 |
100% |
3 |
ELECTRICAL CONNECTIVITY WORKS (BAY LA SUN MV CORRIDOR - PHASE 2) |
United Works General Cont. Est. |
103970 |
5-May-18 |
EMAAR |
6,731,308.30 |
100% |
4 |
LAGOONA MOTOR SPORT PARK RACE TRACK AND KARTING TRACKS CONSTRUCTION |
United Works General Cont. Est. |
103634 |
18-Feb-18 |
EMAAR |
31,877,638.10 |
99% |
5 |
BLS! & PANDA PRIMARY ELECTRICAL INFRA RELOCATION WORK |
United Works General Cont. Est. |
103604 |
8-Nov-17 |
EMAAR |
11,616,774.95 |
100% |
6 |
INDUSTRIAL VALLEY PHASE 2.1 & 2.5 SWALE & FOOTHPATH FOR ROADS |
United Works Genus! Cont. Est. |
103591 |
28-May-17 |
EMAAR |
10,723,517.20 |
100% |
7 |
Z ROAD MISCELLANEOUS IMPROVEMENTS & UTILITY TRUNK LINES TO UTILITY YARD a 2 INFRASTRUCTUREWORKS |
United Works General Cont. Est. |
102862 |
20-Mar-17 |
EMAAR |
10,637,465.30 3 |
100% |
8 |
MOTORSPORT PARK & KAUST (CONSTRUCTION) ROAD GRADING WORKS |
United Works CGeneral Cont. Est. |
103418 |
29-Dec-2016 |
EMAAR |
3,135,000.00 |
100% |
9 |
AL TALAH GARDENS PHASE 2 & 3A INFRASTUCTURE WORKS |
United Works General Cont. Est. |
10100955 |
16-Nov-16 |
EMAAR |
27,979,543.90 |
100% |
10 |
INDUSTRIAL VALLEY 3 - PARCEL B - INFRASTRUCTURE CONSTRUCTION WORKS |
United Works General Cont. Est. |
103120 |
9-Aug-2016 |
EMAAR |
28,312,391.25 |
100% |
I I |
AL MUROOJ PHASE 2 PRIMARY INFRASTRUCTURE WORKS |
United Works General Cont. Est. |
102958 |
14-Apr-2016 |
EMAAR |
16,072,699.50 |
100% |
12 |
AL MUROOJ BEACH COMMUNITY 3 (BC3) INFRASTRUCTURE WORKS |
United Works General Cont. Est |
2049 |
1-May-2016 |
EMAAR |
24,204,729.45 |
100% |
13 |
INDUSTRIAL VALLEY 3 (IV-3) PHASE 1 'C AND PART OF D13ULK EARTHWORKS KAEC |
United Works General Cont. Est. |
102519 |
5-Jan-2016 |
EMAAR |
31,164,551.39 |
100% |
14 |
Al. TALAH GARDENS PRIMARY INFRASTRUCTURE- PHASEI |
United Works General Cont. Est. |
102732 |
15-Nov-2015 |
EMAAR |
25,335,657.05 |
100% |
15 |
ALSHAROOQ PRIMARY INFRASTRUCTURE WORKS |
United Works General Cont. Est.. |
103105 |
30-Jul-2015 |
EMAAR |
1,202,806.00 |
100% |
16 |
HARMAN WADI CHANNEL EARTHWORKS CONSTRUCTION |
United Works General Cont. Est. |
102545 |
30-Apr-2015 |
EMAAR |
1,555,239.26 |
100% |
17 |
INDUSTRIAL VALLEY 2 (IV-2) PHASE 2.2 AND 2.3 EARTHWORKS, KAEC |
United Works Cast Cont. Est. |
102414 |
12-Jan-2014 |
EMAAR |
27,490,320.00 |
100% |
18 |
CONSTRUCTION OF DAMMAM DIE 6B 115KV/13.8KV SUBSTATION CIVIL WORKS |
United Works General Cont. Est. |
450003565 |
14-Jul-2014 |
SAUDI ELECTRICAL COMPANY |
6,437,750.00 |
100% |
19 |
INDUSTRIAL VALLEY (IV) PHASE 2 PRORITY PACKAGE EARTHWORK, |
United Works General Cont. Est. |
2098 |
23-Mar-2014 |
EMAAR |
#VALUE! |
100% |
20 |
WATER NETWORK PROJECT DAMMAM |
United Works General Cont. Est. |
63/01/00/1336/00/4 |
24-Jul-2014 |
SAUDI WATER & ELECTRICAL |
14,804,446.25 |
100% |
21 |
MAIN LIFT STATION, P-14 AND LIFT STATION P-I3 AND SEWERIJNE AT JUBAIL |
United Works General Cont. Est. |
63-01-00-1333-00-4 |
18-Aug-2014 |
SAUDI WATER & ELECTRICAL |
49,500,000.00 |
100% |
22 |
NEIGHBORHOOD 4 DEVELOPMENT PROJECT AT AL KHAFJI |
United Works General Cont. Est. |
HQ060AGOCIO |
27-Sep-2010 |
SAUDI ARAMCO |
36,927,948.75 |
100% |
24 |
ITH RA- ICING ABDUL AZIZ KNOWLEDGE & CULTURE - UTILITIES'DHAHRAN |
United Works General Cont. Est. |
6600022781 |
27/05/2009 |
SAUDI ARAMCO |
37,415,832.30 |
100% |
25 |
INITIAL AND FINAL DEVELOPMENT OF IVO LOTS, ARRABIYAH PHASE 4 |
United Works General Cont. Est. |
6600022159 |
4-Nov-2009 |
SAUDI ARAMCO |
24,133,332.30 |
100% |
26 |
RABIGH CONVERSION INDUSTRIAL PARK DEVELOPMENT PROJECT |
United Works General Cont. Est |
660001950902 |
1-Mar-2009 |
SAUDI ARAMCOSUM1TOM |
166,082,331.80 |
100% |
27 |
CONSTRUCTION OF NON-PROCESS BUILDING AT KHURSANIYAH PRODUCING(KPF) FACILITES |
United Works General Cont. Est. |
6600008004 |
15-Apr-2008 |
SAUDI ARAMCO |
43,092,500.00 |
100% |
28 |
SITE PREPARATION FOR CORPORATE DATA CENTER, DHAHRAN |
United Works General Cont. Est. |
6600018647 |
18-Jun-2007 |
SAUDI ARAMCO |
46,438,631.80 |
100% |